Sequential tDB2Row

I have two DB2Row components connected by a Main flow.
They both operate on the same tables and seem to launch at the same time - thereby locking each other out and my job never finishes.  Each of them executes fine by themselves.

How do I have the second one wait for the first tDB2Row to finish before executing?

Tried the OnComponentOk - but that gave unresolved references in the second tDB2Row.

Offline

#2 2008-05-04 09:07:22

shong
Talend team
Registered: 2007-08-29
Posts: 10310
Website

Re: Sequential tDB2Row

Hello

Tried the OnComponentOk - but that gave unresolved references in the second tDB2Row.

Did you try the 'OnSubJobOK' connector? Can you upload a screenshot of your job?

Best regards

         shong


Email:shong@talend.com
Choose Talend, Enjoy Talend!
New & Event: Talend Help Center