Daisy Chain (Link) Job Designs

Is there any way of using talend to put a process together sheduling job designs sequentially, so that one job wil start once the other has finished?

Offline

#2 2008-05-15 22:44:55

mhirt
Talend team
Registered: 2006-09-19
Posts: 1635

Re: Daisy Chain (Link) Job Designs

Hello

tRunJob -> On Component OK or onSubjobOK -> tRunjob

HTH,